Construction noise in an occupied town square is a boundary problem, not a site problem. The receiver is a few metres away, on the other side of a line you are allowed to occupy, and the cheapest reduction available is almost always at that line.

The B1 screen is a modular system: absorptive panels in steel frames, carried between galvanised posts, with each panel lifted into place and retained on the post rather than welded to it. The face is finished green, which is the usual choice where the screen stands in a residential streetscape and a galvanised sheet would read as a building site.
On this site the posts stand on the paved surface. That detail matters more than it looks: a public square is paved, drained and often has services beneath, so a screen that needs a concrete strip foundation is a screen that needs permits, excavation and reinstatement. A surface-mounted post turns that into an installation.
In an enclosed square a reflective screen does half the job and then undoes part of it. Sound that would have crossed the boundary is turned back into the works, where it strikes the opposite façade, the scaffold, the hoarding on the far side, and comes back. Absorptive panels take a large part of that energy in at the face, which lowers the level inside the works as well as outside it.
The distinction is worth stating plainly, because it is where cheap screens are cheapest: a solid panel is a barrier, an absorptive panel is a barrier plus a treatment. In a street with hard surfaces on both sides, the second is what actually reduces the level at the dwellings.
A works site changes shape every month. A welded screen is built once and then either obstructs the next phase or is cut up and scrapped. Panels that lift out between posts can be moved, re-used at a new boundary, and taken away at the end — which is also why this type of screen is chosen for rented hoarding systems rather than permanent barriers.
Panel change — one damaged or graffitied panel is replaced without touching the rest of the run.
Layout change — corners and returns are made by adding posts, not by fabricating new frames.
Removal — the screen comes out in units that can be transported and stored.
A screen standing on a paved surface is held by its own weight and by whatever ballast the feet carry. A two-metre panel is a sail, and on an exposed corner the wind case governs the design, not the acoustics. Where the screen is tall or the site is windy, the posts are ballasted or anchored, and the layout avoids long unbraced returns.
The other limit is honest: a screen at ground level deals with ground-level sources — cutting, drilling, plant idling at the boundary. It does nothing about a crane lifting thirty metres up, or about impact noise transmitted through the ground. Anyone selling a boundary screen as total site noise control is overselling it.
Panels, frames, posts and retention fittings were manufactured and supplied by Hebei Jinbiao. Installation and ballasting were carried out by the contractor on site.
The same panel system does both. On a works site it is used as relocatable screening; along a road or railway the identical panels are built into a permanent barrier on a proper foundation.
Not if the posts are surface-mounted and ballasted. If the screen is tall, exposed, or has to resist a design wind case rather than just steady breeze, a foundation or a positive anchorage is the correct answer.
Yes. That is the reason for the modular frame and mechanical retention rather than welded connections.
It reduces the level reaching them, provided the screen breaks the path between source and receiver and the panels absorb rather than reflect. The amount is a calculation for the site, not a product figure.