CA Temporary Fence System and Layout
Start From the Corners
A temporary run is set out from its fixed points: the corners, the gates and anything the fence has to meet, such as a building line or a hoarding. The straight runs are filled in afterwards.
Setting out from one end and working forward is what produces an odd panel at the last corner and a gap that has to be closed with a brace.
Foot Placement
Each joint between panels carries a foot, so a run of ten panels on open ground needs eleven feet. Leaving a foot out to save one is the usual cause of a run that leans after a week.
On a hard surface the foot should sit flat and be checked for rocking; a rocking foot works its coupler loose.
Counting the Panels
Divide the boundary length by the panel width and round up, then add the corner and gate modules. A boundary of 60 m with 2.4 m panels needs 25 panels plus corners.
Add a small number of spares: a damaged panel mid-run cannot be pulled back into shape the way a woven mesh can.
Gates in the Layout
Gates are set between panels and need their own posts and feet. A pedestrian gate can hang from a panel upright; a vehicle gate needs a dedicated frame, because the leaf weighs more than a panel.
Put the gates where vehicles will actually go, not where the drawing has room.
Where a Run Needs Bracing
Long straight runs on exposed ground need returns at the ends, heavier feet, or a brace panel set at an angle. A free-standing line with open ends is the shape that fails first in wind.
Where the ground slopes, the run should step rather than follow the slope, so panels stay vertical.